Check
here frequently for updates as the expansion project
progresses.
Date
Status
December
23 , 2009
December
14 , 2009
December
8, 2009
November
28 , 2009
Phase
3 construction is underway:
October
3, 2009
Our
concert fundraiser with groups FACE
and Mile
21 raised $39,068 for the Phase 3 expansion.
Thanks to everyone who donated! Phase 3
construction will begin later this month.
We
have received a new Phase 2 estimate based
on scaled-back criteria. The firm bid is
for $87,000,
which will cover the addition of 3 new classrooms
on the second level. A cement staircase
will be constructed as well. We have advised
the John Wesley School to proceed with this
bid. We expect construction to begin in
late October.
September
27, 2008
Due
to increasing material prices, the final
bid for Phase 2 construction came in at
$138,348.
Steel and cement have skyrocketed in past
months. Due to the increased cost and considering
the donation threshold reached thus far,
we have asked to have Phase 2 construction
re-estimated to include only the addition
of 3 classrooms on the upper level.
September
18, 2008
Our
concert fundraiser with groups FACE
and Mile
21 raised $37,000 for the expansion project.
Thanks to everyone who donated!
March,
2008
We
have received a rough estimate for Phase
2 construction. About $120,000 will be required
to complete the following:
Demolish
and rebuild the administration wing
Build
an additional 3 classrooms on the second
level to accommodate grades 10 - 12.
January
11 , 2008
Phase
1 construction is complete. The quality
of the new classrooms is much beyond expected.
The classrooms are bigger, taller, and brighter.
The kids are very happy with their new school.
Here are some photos
from the dedication ceremony.
October
1, 2007
Final
bids are in, and we have a contract with
a builder. Although the bids came in much
higher than expected, we are still close
to funding the project. The plan is to demolish
and rebuild the two classroom wings in Phase
1. This will provide two additional classrooms
over what they currently have, which will
satisfy local government requirements for
high school class space. Phase 2 will consist
of rebuilding the smaller administration
wing and putting up as much of the second
level as possible.
We
have paid a 40% deposit to the construction
company, and demolition is slated to begin
on October 10th. The builders are confident
they will be able to finish Phase 1 before
school starts in mid-January.
Note
that we are still about $10,000 shy of the
final bid amount. Please contact us if you
would like to help us close the gap before
the end of 2007.
August
7, 2007
After
discussion with the architect and the JW
School principal, we have decided that the
following is the most efficient way to break
down the project:
Phase
1
Demolish
existing building and rebuild first
level such that it can support 2 more
levels. This will provide 2 additional
classrooms by leveraging wasted space
in the current design. (Timeframe: October,
2007 - January, 2008)
Phase
2
Build
second level
Phase
3
Build
third level
Note
that this approach will increase the Phase
1 budget by $15,000. We think that in the
long run, though, this will significantly
reduce the cost and complexity of future
phases.